boeingBoeing's aircraft orders and deliveries fell in January as the company dealt with the fallout from a mid-flight explosion of a fuselage panel on one of its 737 Max 9s, an accident that overshadowed the manufacturer's strong finish to 2023.

The company delivered 27 planes last month, its lowest number since September, compared to 67 deliveries in December. It sold three Boeing 737 Max aircraft, but also recorded three cancellations.

Deliveries were roughly in line with what some analysts expected. The three gross orders come after a big December in which Boeing sold 371 aircraft.

Boeing's rival Airbus delivered 30 planes in January.

Boeing executives have been struggling to persuade airline customers, investors and regulators that they will find a more reliable footing after the Jan. 5 accident, when a door plug exploded in a Alaska Airlines flight at 16,000 feet shortly after leaving Portland, Oregon. No one was seriously injured on Flight 1282, but the violent detail tore off the headrests and exposed travelers to a gaping hole in row 26.

Bolts holding the unused exit door panel in place appeared to be missing from the fuselage piece, which had been removed and replaced at Boeing's 737 Max factory in Renton, Washington, the National Safety Board said. in Transportation in a preliminary report on February 6.

Boeing CEO Dave Calhoun has pledged to review manufacturing processes at the company's facilities. The Federal Aviation Administration said it would pause Boeing's planned production increases until it is “satisfied that the quality control issues discovered during this process are resolved.”

“I'm glad they paused because it's a good excuse to take our time and do it right,” Calhoun said on a Jan. 31 earnings conference call.

Boeing revealed earlier this month that it would have to rework about 50 undelivered Max planes due to improperly drilled holes, a new production issue that could delay deliveries.

The FAA is auditing Boeing production, and the agency's administrator, Mike Whitaker, told CNBC last month that it will keep “boots on the ground” at Boeing and conduct direct inspections of work there. The audit includes about two dozen inspectors, stationed at the Renton factory and in Wichita, Kansas, where Spiritual Aerosystems manufactures Max fuselages.

Boeing now has to periodically pause its production line, and Chief Financial Officer Brian West said at a TD Cowen investor conference on Tuesday that the company expects to have a steady pace of 38 Max jets per month in the second half of the year.

“We're doing it so we can get the benefit of our audit, we can get the benefit of our own inspection protocols, and that will just slow down the line,” West said.

FAA Administrator Whitaker will travel to the Renton plant this week.

Boeing's deliveries in January included three Max jets to Chinese customers, the first in about four years.